Due diligence when selecting contractors or subcontractors
Contents |
[edit] Introduction
The financial failure of a contractor or key supplier can be catastrophic to a project.
To reduce exposure to risks it is important to have a thorough grasp of both the capability and financial status of a prospective organisation before appointing them.
Reliance on credit checks involving accounts filed at Companies House can be useful, as can assessments of past track record, but they have their limitations. It is important to understand where the organisation might be exposed to risks through commitments to, or reliance on, third parties, and how secure and well resourced they are given the size of the proposed contract and their other commitments.
The following issues should be evaluated against the proposed scope of works to be undertaken:
[edit] History
- Track record and appropriate references.
- Audited accounts.
- Tax returns.
[edit] Current position
- Main customers (each expressed as a percentage of total turnover to reveal where there may be significant dependencies).
- Current contracts in progress including project programmes and values (to assess where there may be significant overlaps that would put the organisation under pressure).
- Staff resources and CV’S of senior management.
- Organisation chart.
- Current debt position with debt expiry dates.
- Current direct labour resource, including comparisons with previous years.
- Current subcontractors and suppliers.
- Details of current warrantees, guarantees, encumbrances, liens, performance or on-demand bonds or charges held by third parties.
[edit] Future position
- Pipeline work under tender or negotiation.
- Current unaudited annual accounts in progress.
- Proposed subcontractors and suppliers.
[edit] Legal position
- Litigation, claims and other disputes in progress.
- Ownership of intellectual property, patents, licenses and certification required to carry out the work.
- Insurances in place.
- Partnerships or joint ventures with other organisations.
- Ownership of machinery and facilities required to execute the work.
[edit] Technical capability
- Examination of past or current similar work.
- Competency, qualifications and certificates.
- Subcontractor and supplier capability.
- Building Information Modelling (BIM) capability.
- Overall capacity to undertake the work.
- Disaster planning in the event of a catastrophic occurrence such as fire.
[edit] Other indicators
- The cost of performance bonds.
- Reputation in the insurance market.
- Time taken to pay subcontractors and suppliers.
[edit] Step-by-step guidance on appointing a contractor:
- Traditional contract: tender.
- Design and build: tender.
- Construction management: tender.
- Management contract: tender.
- Public project: tender.
[edit] Related articles on Designing Buildings
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.